Monday 8 June 2015

Project management




From Wikipedia, the free encyclopedia


This is one of a collection of articles which has a direct, or indirect relevance for the development of the UDP. Blogger Ref http://www.p2pfoundation.net/Universal_Debating_Project



Jump to: navigation, search
Project management is the process and activity of planning, organizing, motivating, and controlling resources, procedures and protocols to achieve specific goals in scientific or daily problems. A project is a temporary endeavor designed to produce a unique product, service or result with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables) undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value.[1][2] The temporary nature of projects stands in contrast with business as usual (or operations),[3] which are repetitive, permanent, or semi-permanent functional activities to produce products or services. In practice, the management of these two systems is often quite different, and as such requires the development of distinct technical skills and management strategies.[4]
The primary challenge of project management is to achieve all of the project goals[5] and objectives while honoring the preconceived constraints.[6] The primary constraints are scope, time, quality and budget.[7] The secondary — and more ambitious — challenge is to optimize the allocation of necessary inputs and integrate them to meet pre-defined objectives.


History[edit]



Roman soldiers building a fortress, Trajan's Column 113 AD
Until 1900, civil engineering projects were generally managed by creative architects, engineers, and master builders themselves, for example Vitruvius (first century BC), Christopher Wren (1632–1723), Thomas Telford (1757–1834) and Isambard Kingdom Brunel (1806–1859).[8] It was in the 1950s that organizations started to systematically apply project management tools and techniques to complex engineering projects.[9]


Henry Gantt (1861–1919), the father of planning and control techniques
As a discipline, project management developed from several fields of application including civil construction, engineering, and heavy defense activity.[10] Two forefathers of project management are Henry Gantt, called the father of planning and control techniques,[11] who is famous for his use of the Gantt chart as a project management tool (alternatively Harmonogram first proposed by Karol Adamiecki[12]); and Henri Fayol for his creation of the five management functions that form the foundation of the body of knowledge associated with project and program management.[13] Both Gantt and Fayol were students of Frederick Winslow Taylor's theories of scientific management. His work is the forerunner to modern project management tools including work breakdown structure (WBS) and resource allocation.
The 1950s marked the beginning of the modern project management era where core engineering fields come together to work as one. Project management became recognized as a distinct discipline arising from the management discipline with engineering model.[14] In the United States, prior to the 1950s, projects were managed on an ad-hoc basis, using mostly Gantt charts and informal techniques and tools. At that time, two mathematical project-scheduling models were developed. The "Critical Path Method" (CPM) was developed as a joint venture between DuPont Corporation and Remington Rand Corporation for managing plant maintenance projects. And the "Program Evaluation and Review Technique" or PERT, was developed by the United States Navy in conjunction with the Lockheed Corporation and Booz Allen Hamilton as part of the Polaris missile submarine program.[15]
PERT and CPM are very similar in their approach but still present some differences. CPM is used for projects that assume deterministic activity times; the times at which each activity will be carried out are known. PERT, on the other hand, allows for stochastic activity times; the times at which each activity will be carried out are uncertain or varied. Because of this core difference, CPM and PERT are used in different contexts. These mathematical techniques quickly spread into many private enterprises.


PERT network chart for a seven-month project with five milestones
At the same time, as project-scheduling models were being developed, technology for project cost estimating, cost management, and engineering economics was evolving, with pioneering work by Hans Lang and others. In 1956, the American Association of Cost Engineers (now AACE International; the Association for the Advancement of Cost Engineering) was formed by early practitioners of project management and the associated specialties of planning and scheduling, cost estimating, and cost/schedule control (project control). AACE continued its pioneering work and in 2006 released the first integrated process for portfolio, program and project management (Total Cost Management Framework).
The International Project Management Association (IPMA) was founded in Europe in 1967,[16] as a federation of several national project management associations. IPMA maintains its federal structure today and now includes member associations on every continent except Antarctica. IPMA offers a Four Level Certification program based on the IPMA Competence Baseline (ICB).[17] The ICB covers technical, contextual, and behavioral competencies.
In 1969, the Project Management Institute (PMI) was formed in the USA.[18] PMI publishes A Guide to the Project Management Body of Knowledge (PMBOK Guide), which describes project management practices that are common to "most projects, most of the time." PMI also offers multiple certifications.

Approaches[edit]

There are a number of approaches for managing project activities including lean, iterative, incremental, and phased approaches.
Regardless of the methodology employed, careful consideration must be given to the overall project objectives, timeline, and cost, as well as the roles and responsibilities of all participants and stakeholders.

The traditional approach[edit]

A traditional phased approach identifies a sequence of steps to be completed. In the "traditional approach",[19] five developmental components of a project can be distinguished (four stages plus control):


Typical development phases of an engineering project
  1. initiation
  2. planning and design
  3. execution and construction
  4. monitoring and controlling systems
  5. completion and finish point
Not all projects will have every stage, as projects can be terminated before they reach completion. Some projects do not follow a structured planning and/or monitoring process. And some projects will go through steps 2, 3 and 4 multiple times.
Many industries use variations of these project stages. For example, when working on a brick-and-mortar design and construction, projects will typically progress through stages like pre-planning, conceptual design, schematic design, design development, construction drawings (or contract documents), and construction administration. In software development, this approach is often known as the waterfall model,[20] i.e., one series of tasks after another in linear sequence. In software development many organizations have adapted the Rational Unified Process (RUP) to fit this methodology, although RUP does not require or explicitly recommend this practice. Waterfall development works well for small, well defined projects, but often fails in larger projects of undefined and ambiguous nature. The Cone of Uncertainty explains some of this as the planning made on the initial phase of the project suffers from a high degree of uncertainty. This becomes especially true as software development is often the realization of a new or novel product. In projects where requirements have not been finalized and can change, requirements management is used to develop an accurate and complete definition of the behavior of software that can serve as the basis for software development.[21] While the terms may differ from industry to industry, the actual stages typically follow common steps to problem solving—"defining the problem, weighing options, choosing a path, implementation and evaluation."

PRINCE2[edit]

Main article: PRINCE2


The PRINCE2 process model
PRINCE2 is a structured approach to project management released in 1996 as a generic project management method.[22] It combines the original PROMPT methodology (which evolved into the PRINCE methodology) with IBM's MITP (managing the implementation of the total project) methodology. PRINCE2 provides a method for managing projects within a clearly defined framework.
PRINCE2 focuses on the definition and delivery of products, in particular their quality requirements. As such, it defines a successful project as being output-oriented (not activity- or task-oriented) through creating an agreed set of products[23] that define the scope of the project and provides the basis for planning and control, that is, how then to coordinate people and activities, how to design and supervise product delivery, and what to do if products and therefore the scope of the project has to be adjusted if it does not develop as planned.
In the method, each process is specified with its key inputs and outputs and with specific goals and activities to be carried out to deliver a project's outcomes as defined by its Business Case. This allows for continuous assessment and adjustment when deviation from the Business Case is required.
PRINCE2 provides a common language for all participants in the project. The governance framework of PRINCE2 – its roles and responsibilities – are fully described and require tailoring to suit the complexity of the project and skills of the organisation.[23]

Critical chain project management[edit]

Critical chain project management (CCPM) is a method of planning and managing project execution designed to deal with uncertainties inherent in managing projects, while taking into consideration limited availability of resources (physical, human skills, as well as management & support capacity) needed to execute projects.
CCPM is an application of the theory of constraints (TOC) to projects. The goal is to increase the flow of projects in an organization (throughput). Applying the first three of the five focusing steps of TOC, the system constraint for all projects is identified as are the resources. To exploit the constraint, tasks on the critical chain are given priority over all other activities. Finally, projects are planned and managed to ensure that the resources are ready when the critical chain tasks must start, subordinating all other resources to the critical chain.
The project plan should typically undergo resource leveling, and the longest sequence of resource-constrained tasks should be identified as the critical chain. In some cases, such as managing contracted sub-projects, it is advisable to use a simplified approach without resource leveling.
In multi-project environments, resource leveling should be performed across projects. However, it is often enough to identify (or simply select) a single "drum". The drum can be a resource that acts as a constraint across projects, which are staggered based on the availability of that single resource.
One can also use a "virtual drum" by selecting a task or group of tasks (typically integration points) and limiting the number of projects in execution at that stage.

Process-based management[edit]

The incorporation of process-based management has been driven by the use of Maturity models such as the CMMI (capability maturity model integration; see this example of a predecessor) and ISO/IEC15504 (SPICE – software process improvement and capability estimation).

Agile project management[edit]



The iteration cycle in agile project management
Agile project management encompasses several iterative approaches, based on the principles of human interaction management and founded on a process view of human collaboration. Agile-based methodologies are "most typically" employed in software development as well as the "website, technology, creative, and marketing industries."[24] This sharply contrasts with traditional approaches such as the Waterfall method. In agile software development or flexible product development, the project is seen as a series of relatively small tasks conceived and executed to conclusion as the situation demands in an adaptive manner, rather than as a completely pre-planned process.
Advocates of this technique claim that:
  • It is the most consistent project management technique since it involves frequent testing of the project under development.
  • It is the only technique in which the client will be actively involved in the project development.
  • The only disadvantage with this technique is that it should be used only if the client has enough time to be actively involved in the project every now and then.
Agile is an umbrella term for multiple project management methodologies, including:
  • Scrum - A holistic approach to development that focuses on iterative goals set by the Product Owner through a backlog, which is developed by the Delivery Team through the facilitation of the Scrum Master.
  • Extreme Programming (XP) - A set of practices based on a set of principles and values, with a goal to develop that provides real value by implementing tight feedback loops at all levels of the development process and using them to steer development. XP popularized Test Driven Development (TDD) and Pair Programming.
  • eXtreme Manufacturing (XM) - An agile methodology based on Scrum, Kanban and Kaizen that facilitates rapid engineering and prototyping.
  • Crystal Clear - An agile or lightweight methodology that focuses on colocation and osmotic communication.
  • Kanban (かんばん(看板)?) - A lean framework for process improvement that is frequently used to manage work in progress (WIP) within agile projects. Kanban has been specifically applied in software development.
  • Scrum ban a mixed scrum and kanban approach to project management. It focuses on taking the flexibility of kanban and adding the structure of scrum to create a new way to manage projects.

Lean project management[edit]

Lean project management uses the principles from lean manufacturing to focus on delivering value with less waste and reduced time.

Extreme project management[edit]



Planning and feedback loops in Extreme programming (XP) with the time frames of the multiple loops.
In critical studies of project management it has been noted that several PERT based models are not well suited for the multi-project company environment of today.[citation needed] Most of them are aimed at very large-scale, one-time, non-routine projects, and currently all kinds of management are expressed in terms of projects.
Using complex models for "projects" (or rather "tasks") spanning a few weeks has been proven to cause unnecessary costs and low maneuverability in several cases.[citation needed] The generalization of Extreme Programming to other kinds of projects is extreme project management, which may be used in combination with the process modeling and management principles of human interaction management.

Benefits realization management[edit]

Benefits realization management (BRM) enhances normal project management techniques through a focus on outcomes (the benefits) of a project rather than products or outputs, and then measuring the degree to which that is happening to keep a project on track. This can help to reduce the risk of a completed project being a failure by delivering agreed upon requirements/outputs but failing to deliver the benefits of those requirements.
In addition, BRM practices aim to ensure the alignment between project outcomes and business strategies. The effectiveness of these practices is supported by recent research evidencing BRM practices influencing project success from a strategic perspective across different countries and industries.[25]
An example of delivering a project to requirements might be agreeing to deliver a computer system that will process staff data and manage payroll, holiday and staff personnel records. Under BRM the agreement might be to achieve a specified reduction in staff hours required to process and maintain staff data.

Processes[edit]



The project development stages[26]
Traditionally, project management includes a number of elements: four to five process groups, and a control system. Regardless of the methodology or terminology used, the same basic project management processes will be used. Major process groups generally include:[7]
  • Initiation
  • Planning or design
  • Production or execution
  • Monitoring and controlling
  • Closing
In project environments with a significant exploratory element (e.g., research and development), these stages may be supplemented with decision points (go/no go decisions) at which the project's continuation is debated and decided. An example is the Phase–gate model.

Initiating[edit]



Initiating process group processes[26]
The initiating processes determine the nature and scope of the project.[27] If this stage is not performed well, it is unlikely that the project will be successful in meeting the business’ needs. The key project controls needed here are an understanding of the business environment and making sure that all necessary controls are incorporated into the project. Any deficiencies should be reported and a recommendation should be made to fix them.
The initiating stage should include a plan that encompasses the following areas:

Planning and design[edit]

After the initiation stage, the project is planned to an appropriate level of detail (see example of a flow-chart).[26] The main purpose is to plan time, cost and resources adequately to estimate the work needed and to effectively manage risk during project execution. As with the Initiation process group, a failure to adequately plan greatly reduces the project's chances of successfully accomplishing its goals.
Project planning generally consists of[28]
  • determining how to plan (e.g. by level of detail or rolling wave);
  • developing the scope statement;
  • selecting the planning team;
  • identifying deliverables and creating the work breakdown structure;
  • identifying the activities needed to complete those deliverables and networking the activities in their logical sequence;
  • estimating the resource requirements for the activities;
  • estimating time and cost for activities;
  • developing the schedule;
  • developing the budget;
  • risk planning;
  • gaining formal approval to begin work.
Additional processes, such as planning for communications and for scope management, identifying roles and responsibilities, determining what to purchase for the project and holding a kick-off meeting are also generally advisable.
For new product development projects, conceptual design of the operation of the final product may be performed concurrent with the project planning activities, and may help to inform the planning team when identifying deliverables and planning activities.

Executing[edit]



Executing process group processes[26]
Executing consists of the processes used to complete the work defined in the project plan to accomplish the project's requirements.

Monitoring and controlling[edit]



Monitoring and controlling process group processes[26]
Monitoring and controlling consists of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken, when necessary, to control the execution of the project. The key benefit is that project performance is observed and measured regularly to identify variances from the project management plan.
Monitoring and controlling includes:[29]
  • Measuring the ongoing project activities ('where we are');
  • Monitoring the project variables (cost, effort, scope, etc.) against the project management plan and the project performance baseline (where we should be);
  • Identify corrective actions to address issues and risks properly (How can we get on track again);
  • Influencing the factors that could circumvent integrated change control so only approved changes are implemented.
In multi-phase projects, the monitoring and control process also provides feedback between project phases, in order to implement corrective or preventive actions to bring the project into compliance with the project management plan.
Project maintenance is an ongoing process, and it includes:[7]
  • Continuing support of end-users
  • Correction of errors
  • Updates of the software over time


Monitoring and controlling cycle
In this stage, auditors should pay attention to how effectively and quickly user problems are resolved.
Over the course of any construction project, the work scope may change. Change is a normal and expected part of the construction process. Changes can be the result of necessary design modifications, differing site conditions, material availability, contractor-requested changes, value engineering and impacts from third parties, to name a few. Beyond executing the change in the field, the change normally needs to be documented to show what was actually constructed. This is referred to as change management. Hence, the owner usually requires a final record to show all changes or, more specifically, any change that modifies the tangible portions of the finished work. The record is made on the contract documents – usually, but not necessarily limited to, the design drawings. The end product of this effort is what the industry terms as-built drawings, or more simply, “as built.” The requirement for providing them is a norm in construction contracts. Construction document management is a highly important task undertaken with the aid an online or desktop software system, or maintained through physical documentation. The increasing legality pertaining to the construction industries maintenance of correct documentation has caused the increase in the need for document management systems.
When changes are introduced to the project, the viability of the project has to be re-assessed. It is important not to lose sight of the initial goals and targets of the projects. When the changes accumulate, the forecasted result may not justify the original proposed investment in the project. Successful project management identifies these components, and tracks and monitors progress so as to stay within time and budget frames already outlined at the commencement of the project.

Closing[edit]



Closing process group processes.[26]
Closing includes the formal acceptance of the project and the ending thereof. Administrative activities include the archiving of the files and documenting lessons learned.
This phase consists of:[7]
  • Contract closure: Complete and settle each contract (including the resolution of any open items) and close each contract applicable to the project or project phase.
  • Project close: Finalize all activities across all of the process groups to formally close the project or a project phase
Also included in this phase is the Post Implementation Review. This is a vital phase of the project for the project team to learn from experiences and apply to future projects. Normally a Post Implementation Review consists of looking at things that went well and analysing things that went badly on the project to come up with lessons learned.

Project controlling and project control systems[edit]

Project controlling should be established as an independent function in project management. It implements verification and controlling function during the processing of a project in order to reinforce the defined performance and formal goals.[30] The tasks of project controlling are also:
  • the creation of infrastructure for the supply of the right information and its update
  • the establishment of a way to communicate disparities of project parameters
  • the development of project information technology based on an intranet or the determination of a project key performance indicator system (KPI)
  • divergence analyses and generation of proposals for potential project regulations[31]
  • the establishment of methods to accomplish an appropriate project structure, project workflow organization, project control and governance
  • creation of transparency among the project parameters[32]
Fulfillment and implementation of these tasks can be achieved by applying specific methods and instruments of project controlling. The following methods of project controlling can be applied:
  • investment analysis
  • cost–benefit analysis
  • value benefit analysis
  • expert surveys
  • simulation calculations
  • risk-profile analysis
  • surcharge calculations
  • milestone trend analysis
  • cost trend analysis
  • target/actual-comparison[33]
Project control is that element of a project that keeps it on-track, on-time and within budget.[29] Project control begins early in the project with planning and ends late in the project with post-implementation review, having a thorough involvement of each step in the process. Projects may be audited or reviewed while the project is in progress. Formal audits are generally risk or compliance-based and management will direct the objectives of the audit. An examination may include a comparison of approved project management processes with how the project is actually being managed.[34] Each project should be assessed for the appropriate level of control needed: too much control is too time consuming, too little control is very risky. If project control is not implemented correctly, the cost to the business should be clarified in terms of errors and fixes.
Control systems are needed for cost, risk, quality, communication, time, change, procurement, and human resources. In addition, auditors should consider how important the projects are to the financial statements, how reliant the stakeholders are on controls, and how many controls exist. Auditors should review the development process and procedures for how they are implemented. The process of development and the quality of the final product may also be assessed if needed or requested. A business may want the auditing firm to be involved throughout the process to catch problems earlier on so that they can be fixed more easily. An auditor can serve as a controls consultant as part of the development team or as an independent auditor as part of an audit.
Businesses sometimes use formal systems development processes. These help assure that systems are developed successfully. A formal process is more effective in creating strong controls, and auditors should review this process to confirm that it is well designed and is followed in practice. A good formal systems development plan outlines:
  • A strategy to align development with the organization’s broader objectives
  • Standards for new systems
  • Project management policies for timing and budgeting
  • Procedures describing the process
  • Evaluation of quality of change

Topics[edit]

Project managers[edit]

A project manager is a professional in the field of project management. Project managers can have the responsibility of the planning, execution, and closing of any project, typically relating to construction industry, engineering, architecture, computing, and telecommunications. Many other fields in production engineering, design engineering, and heavy industrial have project managers.
A project manager is the person accountable for accomplishing the stated project objectives. Key project management responsibilities include creating clear and attainable project objectives, building the project requirements, and managing the triple constraint for projects, which is cost, time, and scope.
A project manager is often a client representative and has to determine and implement the exact needs of the client, based on knowledge of the firm they are representing. The ability to adapt to the various internal procedures of the contracting party, and to form close links with the nominated representatives, is essential in ensuring that the key issues of cost, time, quality and above all, client satisfaction, can be realized.

Project management types[edit]

While Project management, by itself, is a discipline that can apply to any project intended to deliver solutions for any purpose, it is often tailored to accommodate the specific and repeatable needs of different and highly specialized industries. For example, the construction industry, which focuses on the delivery of things like buildings, roads, and bridges, has developed its own specialized form of project management that it refers to as Construction project management and for which project managers can become trained and certified in.[35] The Information technology industry has also evolved to develop its own form of Project management that is referred to as IT Project management and which specializes in the delivery of technical assets and services that are required to pass through various lifecycle phases such as planning, design, development, testing, and deployment. Biotechnology project management focuses on the intricacies of biotechnology research and development.[36]
For each type of project management, project managers develop and utilize repeatable templates that are specific to the industry they're dealing with. This allows project plans to become very thorough and highly repeatable, with the specific intent to increase quality, lower delivery costs, and lower time to deliver project results.

Work breakdown structure[edit]

The work breakdown structure (WBS) is a tree structure that shows a subdivision of effort required to achieve an objective—for example a program, project, and contract. The WBS may be hardware-, product-, service-, or process-oriented (see an example in a NASA reporting structure (2001)).[37]
A WBS can be developed by starting with the end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g., systems, subsystems, components, tasks, sub-tasks, and work packages), which include all steps necessary to achieve the objective.[21]
The work breakdown structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established.[37] The work breakdown structure can be displayed in two forms one in form of a table with subdivision of tasks two in form of an organisational chart.

International standards[edit]

There have been several attempts to develop project management standards, such as:

Project portfolio management[edit]

An increasing number of organizations are using, what is referred to as, project portfolio management (PPM) as a means of selecting the right projects and then using project management techniques[40] as the means for delivering the outcomes in the form of benefits to the performing private or not-for-profit organization.

Project management software[edit]

Project management software is software used to help plan, organize, and manage resource pools, develop resource estimates and implement plans. Depending on the sophistication of the software, functionality may include estimation and planning, scheduling, cost control and budget management, resource allocation, collaboration software, communication, decision-making, workflow, quality management, documentation and/or administration systems.[41][42]

Virtual project management[edit]

Main article: Virtual team
Virtual program management (VPM) is management of a project done by a virtual team, though it rarely may refer to a project implementing a virtual environment[43] It is noted that managing a virtual project is fundamentally different from managing traditional projects,[44] combining concerns of telecommuting and global collaboration (culture, timezones, language).[45]

See also[edit]

References[edit]

  1. Jump up ^ *The Definitive Guide to Project Management. Nokes, Sebastian. 2nd Ed.n. London (Financial Times / Prentice Hall): 2007. ISBN 978-0-273-71097-4
  2. Jump up ^ "What is Project Management? | Project Management Institute". Pmi.org. Retrieved 2014-06-04. 
  3. Jump up ^ Paul C. Dinsmore et al (2005) The right projects done right! John Wiley and Sons, 2005. ISBN 0-7879-7113-8. p.35 and further.
  4. Jump up ^ Cattani, G., Ferriani, S., Frederiksen, L. and Florian, T. (2011) Project-Based Organizing and Strategic Management, Advances in Strategic Management, Vol 28, Emerald, ISBN 1780521936.[1]
  5. Jump up ^ Lewis R. Ireland (2006) Project Management. McGraw-Hill Professional, 2006. ISBN 0-07-147160-X. p.110.
  6. Jump up ^ Joseph Phillips (2003). PMP Project Management Professional Study Guide. McGraw-Hill Professional, 2003. ISBN 0-07-223062-2 p.354.
  7. ^ Jump up to: a b c d PMI (2010). A Guide to the Project Management Body of Knowledge p.27-35
  8. Jump up ^ Dennis Lock (2007) Project Management (9th ed.) Gower Publishing, Ltd., 2007. ISBN 0-566-08772-3
  9. Jump up ^ Young-Hoon Kwak (2005). "A brief History of Project Management". In: The story of managing projects. Elias G. Carayannis et al. (9 eds), Greenwood Publishing Group, 2005. ISBN 1-56720-506-2
  10. Jump up ^ David I. Cleland, Roland Gareis (2006). Global Project Management Handbook. "Chapter 1: "The evolution of project management". McGraw-Hill Professional, 2006. ISBN 0-07-146045-4
  11. Jump up ^ Martin Stevens (2002). Project Management Pathways. Association for Project Management. APM Publishing Limited, 2002 ISBN 1-903494-01-X p.xxii
  12. Jump up ^ Edward R. Marsh (1975). "The Harmonogram of Karol Adamiecki". In: The Academy of Management Journal. Vol. 18, No. 2 (Jun., 1975), p. 358. (online)
  13. Jump up ^ Morgen Witzel (2003). Fifty key figures in management. Routledge, 2003. ISBN 0-415-36977-0. p. 96-101.
  14. Jump up ^ David I. Cleland, Roland Gareis (2006). Global Project Management Handbook. McGraw-Hill Professional, 2006. ISBN 0-07-146045-4. p.1-4 states: "It was in the 1950s when project management was formally recognized as a distinct contribution arising from the management discipline."
  15. Jump up ^ B. Ralph Stauber, H. M. Douty, Willard Fazar, Richard H. Jordan, William Weinfeld and Allen D. Manvel. Federal Statistical Activities. The American Statistician 13(2): 9-12 (Apr., 1959) , pp. 9-12
  16. Jump up ^ Bjarne Kousholt (2007). Project Management –. Theory and practice.. Nyt Teknisk Forlag. ISBN 87-571-2603-8. p.59.
  17. Jump up ^ ipma.ch
  18. Jump up ^ F. L. Harrison, Dennis Lock (2004). Advanced project management: a structured approach. Gower Publishing, Ltd., 2004. ISBN 0-566-07822-8. p.34.
  19. Jump up ^ Wysocki, Robert K (Robert K). Effective Project Management: Traditional, Adaptive, Extreme.  Check date values in: |date= (help)
  20. Jump up ^ Winston W. Royce (1970). "Managing the Development of Large Software Systems" in: Technical Papers of Western Electronic Show and Convention (WesCon) August 25–28, 1970, Los Angeles, USA.
  21. ^ Jump up to: a b Stellman, Andrew; Greene, Jennifer (2005). Applied Software Project Management. O'Reilly Media. ISBN 978-0-596-00948-9. 
  22. Jump up ^ OGC – PRINCE2 – Background
  23. ^ Jump up to: a b [Office for Government Commerce (1996) Managing Successful Projects with PRINCE2, p14]
  24. Jump up ^ "What is Agile Project Management?". Planbox. 
  25. Jump up ^ Serra, C. E. M. & Kunc, M., 2014. Benefits Realisation Management and its influence on project success and on the execution of business strategies. Also, no. International Journal of Project Management, Issue http://dx.doi.org/10.1016/j.ijproman.2014.03.011.
  26. ^ Jump up to: a b c d e f "Project Management Guide" (PDF). VA Office of Information and Technology. 2003. 
  27. Jump up ^ Peter Nathan, Gerald Everett Jones (2003). PMP certification for dummies. p.63.
  28. Jump up ^ Harold Kerzner (2003). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (8th Ed. ed.). Wiley. ISBN 0-471-22577-0. 
  29. ^ Jump up to: a b James P. Lewis (2000). The project manager's desk reference: : a comprehensive guide to project planning, scheduling, evaluation, and systems. p.185
  30. Jump up ^ Jörg Becker, Martin Kugeler, Michael Rosemann (2003). Process management: a guide for the design of business processes. ISBN 978-3-540-43499-3. p.27.
  31. Jump up ^ Bernhard Schlagheck (2000). Objektorientierte Referenzmodelle für das Prozess- und Projektcontrolling. Grundlagen – Konstruktionen – Anwendungsmöglichkeiten. ISBN 978-3-8244-7162-1. p.131.
  32. Jump up ^ Josef E. Riedl (1990). Projekt – Controlling in Forschung und Entwicklung. ISBN 978-3-540-51963-8. p.99.
  33. Jump up ^ Steinle, Bruch, Lawa (1995). Projektmanagement. FAZ Verlagsbereich Wirtschaftsbücher. p.136–143
  34. Jump up ^ Cynthia Snyder, Frank Parth (2006). Introduction to IT Project Management. p.393-397
  35. Jump up ^ "Certified Construction Manager". CMAA. Retrieved 23 November 2013. 
  36. Jump up ^ "Certificate in Biotechnology Project Management". University of Washington. Retrieved 23 November 2013. 
  37. ^ Jump up to: a b NASA NPR 9501.2D. May 23, 2001.
  38. Jump up ^ ISO/IEC/IEEE 16326-2009 - Systems and Software Engineering--Life Cycle Processes--Project Management. December 2009. DOI: 10.1109/IEEESTD.2009.5372630. ISBN 978-0-7381-6116-7
  39. Jump up ^ Body of Knowledge 5th edition, Association for Project Management, 2006, ISBN 1-903494-13-3
  40. Jump up ^ Albert Hamilton (2004). Handbook of Project Management Procedures. TTL Publishing, Ltd. ISBN 0-7277-3258-7
  41. Jump up ^ PMBOK 4h Ed. p. 443. ISBN 978-1933890517. 
  42. Jump up ^ Tom Kendrick. The Project Management Tool Kit: 100 Tips and Techniques for Getting the Job Done Right, Third Edition. AMACOM Books, 2013 ISBN 9780814433454
  43. Jump up ^ Curlee, Wanda (2011). The Virtual Project Management Office: Best Practices, Proven Methods. 
  44. Jump up ^ Khazanchi, Deepak (2005). Patterns of Effective Project Management in Virtual Projects: An Exploratory Study. Project Management Institute. ISBN 9781930699830. 
  45. Jump up ^ Velagapudi, Mridula (April 13, 2012). "Why You Cannot Avoid Virtual Project Management 2012 Onwards". 


External links[edit]

1 comment:

  1. The eco technologies
    The construction of adobe houses has been a popular choice since the earliest settlers.
    La pagina sobre Arquitectura mas chida.
    Parametric architecture

    ReplyDelete

Memo from Winston Churchil to his Staff, 1940

  An important example of the need to simplify information...ideally of all kinds...The piece below comes from the magazine produced by Weth...